A large wind farm wanted 122 wind turbines constructed and fully operational within four months. The project required 400 kW and six hours of run time per turbine. There was no available power grid, as the grid was not scheduled to be available until later that year.
The timeframe was non-negotiable as the project needed to be completed in time to meet a deadline to qualify for a significant tax credit. With such an aggressive schedule, completing the wind turbine testing represented a daunting task.
The Wind Farm selected the world leader in load banks solutions for the wind farm maintenance project. Comrent coordinated and led a team with representatives from all involved stakeholders: the project developer, the wind turbine manufacturer, the electrical engineer of record, and portable generator experts, Aggreko.
To get these wind turbines commissioned in time for the tax credit, the wind farm needed a reliable source of backfeed power. The team designed and built a 3 MW temporary grid emulation complete with diesel generators, resistive and reactive load banks, circuit breakers, transformers, fuel tanks and more than 6,000 feet of electrical cable. Realistic conditions were created for the testing phase so the wind
turbines could be safely put through their paces in a controlled environment.
With the temporary grid-emulation in place, the wind farm maintenance and commissioning was scheduled 12 hours a day, six days a week. No time was lost in testing. The wind turbine testing was successful for startup and operation,
including protection systems.
A large wind farm wanted 122 wind turbines constructed and fully operational within four months. The project required 400 kW and six hours of run time per turbine. There was no available power grid, as the grid was not scheduled to be available until later that year.
The timeframe was non-negotiable as the project needed to be completed in time to meet a deadline to qualify for a significant tax credit. With such an aggressive schedule, completing the wind turbine testing represented a daunting task.
Comrent was able to complete this complicated, quick-turn job within the required four-month timeframe. The successful wind farm maintenance and commissioning demonstrated a fully compliant wind farm that was 100% ready to go once the grid was connected. And the developers met the deadline to claim their tax incentive!
STATS
122 Turbines to test
3 MW- Temporary Grid Emulation
400 kW – Power per turbine
6,000 ft. – Cabling
Do you have a question? Connect with one of our experts. Please fill out the form and a member of our team will contact you within one business day.
The rich text element allows you to create and format headings, paragraphs, blockquotes, images, and video all in one place instead of having to add and format them individually. Just double-click and easily create content.
A rich text element can be used with static or dynamic content. For static content, just drop it into any page and begin editing. For dynamic content, add a rich text field to any collection and then connect a rich text element to that field in the settings panel. Voila!
Headings, paragraphs, blockquotes, figures, images, and figure captions can all be styled after a class is added to the rich text element using the "When inside of" nested selector system.
Do you have a question? Connect with one of our experts. Please fill out the form and a member of our team will contact you within one business day.